Sunday 8 July 2012

Further new from Heights Holdings :  9 July 2012

"Laguna BayConstruction Update

All structural work at Laguna Bay is complete. Interior plastering work is set to complete this month (July 2012). Painting of the exterior skeleton and interior walls continues, currently standing at 39% complete. Ceiling and tiling works within apartments stand at 22% and 19% complete, respectively.

Electrical sytems are now in place across over 75% of apartments, whilst the building's sanitary system is 39% complete. Work on the building's fire alarm (35% complete) and air conditioning systems (25% complete) is well underway. Installation of electrics for corridor lighting in Laguna Bay began at the beginning of the month (July 2012).

The excellent progress made at Laguna Bay by primary contractor Siam Construction has enabled us (Heights Holdings) to bring forward our estimated completion date from April 2013 to December 2012."

No comments:

Post a Comment