Thursday 13 December 2012

Laguna Beach Resort by Heights Holdings

Construction updates provided by the Developer on 4 December 2012:


All piling and foundation works are complete for Building A of Laguna Beach Resort Jomtien. Pouring of concrete for the basement floor is complete and all steel retaining walls are in place for the basement floor. Pouring of concrete for the basement walls of Building A is expected to commence imminently.

Excavation work continues at Building B and work on the foundations has begun. The cutting of piles is in progress, with dynamic load tests complete. 

For availability and prices please call Robert on 08 1938 8391

No comments:

Post a Comment